30.06.2020
Outage Activities of 2020
With the view of implementing outage-2020 covering a large scope of activities to be performed in the framework of the ANPP life extension program the ANPP Unit 2 shutdown is planned for July 1, 2020 at 00:00 and the start-up is planned in 65 days, on 3 September. The following main activities are scheduled to be performed during the outage:
1. reactor intermediate maintenance
2. general overhaul of 2 reactor coolant pumps
3. technical inspection of 6 steam generators
4. installation of a new computer information system
5. survey of drives of emergency shutdown, regulating and shim assemblies
6. routine maintenance of steam turbines №3 and 4
7. general overhaul of turbine generator №3
8. activities on flaw inspection of weld seams of metal of the main circulation pipelines and main stop valves.