REACTOR DEPARTMENT

07.08.2020

REACTOR DEPARTMENT

The activities, aimed at the plant life extension, as part of the outage.

During outage-2020 in the framework of the ANPP life extension program the following main activities are being performed in the Reactor Department.

1. replacement and general overhaul of reactor coolant pumps (RCPs №1 and 6) with replacement of guiding devices by the ANPP specialists,

  1. inspection of the primary circuit headers of all the six steam generators (SGs-1÷6) with inspection of studs and stud seats of the primary and secondary circuit covers by the representatives of the “INETEC”,
  2. inspection of longitudinal and circumferential weld seams of main circulation pipeline (MCP), main stop valves (MSV) and reactor coolant pumps (RCP) by the representatives of the “ECHO+”,
  3. inspection of the reactor coolant pumps cooling pipeline manifold by the ANPP specialists,
  4. replacement of some valves on safety systems with new ones.